Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
Community
Ask the community for help and clear up your study doubts
Discover the best universities in your country according to Docsity users
Free resources
Download our free guides on studying techniques, anxiety management strategies, and thesis advice from Docsity tutors
<div><br /></div><div>EOQ, ISO, TQM, MRP, Break Even Point, plant manager, aggregate production planning, types of manufacturing process, concurrent engineering, intermittent and continuous production system, types of plant layout, cellular layout, Operations Scheduling, information technology</div><div><br /></div><div><br /></div>
Typology: Study notes
1 / 2
This page cannot be seen from the preview
Don't miss anything!
1
_Seat o.: _____ Enrolment o._______
MBA. Second Semester ( Regular / Evening ) Examination May 2010
Date: 27 / 05 / 2010 Time: 11.00 am – 01.30 pm Total Marks: 70
**1. Attempt all questions.
Q.1 (a) 1. Define the following terms in brief: (a) EOQ (b) Productivity (c) Andons (d) ISO (e) Break Even Point (f) TQM (g) Kaizen
(b) What do you mean by JIT? Explain the basic elements of JIT. 07
Q.2 (a) As a plant manager of ceramics products, how will you select the appropriate location of plant? Discuss consideration of various factors affecting it.
(b) What is meant by aggregate production planning? Why it is required? 07 OR (b) Explain the types of manufacturing process in brief. 07
Q.3 (a) Answer the following questions in brief:
(b) Define the various types of plant layout in brief with suitable examples of each.
Q.3 (a) What is MRP? What are the inputs and outputs required by the MRP processing logic?
(b) What is a cellular layout? How is it different from a process layout? How is group technology useful in cellular layout?
Q.4 (a) What do you understand by Operations Scheduling? What are the problems faced in the absence of proper scheduling?
(b) Indira Bank is considering opening a cash transaction window for customer service in the major export show. Management estimates that customers will arrive at the rate of 12 per hour. The teller who will staff the window can service customers at the rate of one every four minutes. Assuming Poisson arrivals and exponential service, find:
Q.4 (a) What do you mean by Demand Forecasting? Explain the various qualitative methods of demand forecasting in brief.
2
(b) (^) Activity Predecessor Time Period (Weeks) A ---- 2 B A 3 C A 4 D B,C 5 E D 3 F D 4 G B,C 5 H E 2 I G,F 3 J H,I 4
Q.5 (a) What do you mean by six-sigma? Explain the various analytical tools associated with six-sigma.
(b) An auto industry purchases spark plugs at the rate of Rs. 35 per piece. The annual consumption of spark plug is 20000 nos. If the ordering cost is Rs. 350 per order and carrying cost is 30% p.a. Find out EOQ and time between orders assuming 360 working days? If he supplies of spark plugs offers a discount of 5% for order quantity of 2000 nos. per order, do you accept the discount offer? Bank rate of interest is 5% and obsolescence cost is Rs. 35000.
Q.5 (a) Discuss the importance of information technology in managing supply chain. 07 (b) An oil packaging company wants the oil to be packed must be exactly 10 liter with a tolerance of + 0.5 liter. The packaging process had a process mean of 9.85 liter and a standard deviation of 0.12 liter. Find out process capability ratio and process capability index and comment on it.