Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
Community
Ask the community for help and clear up your study doubts
Discover the best universities in your country according to Docsity users
Free resources
Download our free guides on studying techniques, anxiety management strategies, and thesis advice from Docsity tutors
project management scope management
Typology: Study notes
1 / 9
This page cannot be seen from the preview
Don't miss anything!
This template is downloaded from project-management.magt.biz
[Company] [Company Address]
Tel: Fax:
[Company Phone] [Company Fax] [Company E-mail]
May 16, 2015 [Ref. number]
Marc Arnecke, PMP
The project scope management plan is a component of the project management plan that describes how the scope will be defined, developed, monitored, controlled, and verified.
[Project Name] Project Scope Management Plan
Marc Arnecke, PMP [Ref. number] II
Revision Release date
Distributed to*
Client Consultant JV Main office(s) All project mgmt. dept.
Sub
Rev. 0 (draft) 29/10/
*) Detailed distribution lists shall be prepared for each distribution event. Further details as per the project communication plan
The Project Scope Management Planfrom time to time may require updates. Any amendment to this plan shall be informed to the change control board by use of the change request form and approved by the project change control board prior to distribution. Only revised parts of the plan will be distributed along with the approval and shall be accompanied by instructions how to implement the changes. The initial page numbering system (to be added upon initial approval) will be a normal continuous numbering displayed in the lower right corner of each page. In the event that pages have to be added, characters shall be added to the number. In case entire pages are deleted, the corresponding page shall be replaced by a blank page stating “page removed”. Each added/changed page shall have the revision number and date of approval displayed on the bottom of the page.
Project Scope Management Plan Marc Arnecke, PMP [Ref. number] IV
[Project Name] Project Scope Management Plan
Marc Arnecke, PMP [Ref. number] 1
Give a brief explanation how the scope will be defined, developed, monitored, controlled, and verified.
This Project Scope Management Planplan forms part of the overall project management plan. Further project plans to be read in conjunction to this project quality management plan are: a) Project Management Plan, b) (this Project Scope Management Plan), c) Project Requirements Management Plan, d) Project Schedule Management Plan, e) Project Cost Management Plan, f) Project Quality Management Plan, g) Process Improvement Plan, h) Project Human Resource Management Plan, i) Project Communication Management Plan, j) Project Risk Management Plan, k) Project Procurement Management Plan, l) Project Stakeholder Management Plan, m) Project Financial Management Plan, n) Project Health and Safety Management Plan, o) Project Environmental Management Plan, p) Project Claim Management Plan.
[Project Name] Project Scope Management Plan
Marc Arnecke, PMP [Ref. number] 3
xxx
Deliverables are any unique and verifiable products, results, or capabilities to perform a service that is required to be produced to complete a process, phase, or project.
A set of conditions that is required to be met before deliverables are accepted.
xxx
Constraints are limiting factors (with regards to the product scope).
Assumptions are factors (with regards to scope) that are considered to be true, real, or certain, without proof or demonstration.
[Project Name] Project Scope Management Plan
Marc Arnecke, PMP [Ref. number] 4
The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. Taking into consideration the importance and the possible size of the WBS, it may be better attached to this scope management plan as a separate document. The WBS can be prepared in different ways including commonly used project management software such as MS Project, Primavera or others.