CVEN 303 - Final Exam Questions with 100 % Correct Answers | Verified, Exams of Advanced Education

Closure Error - CORRECT ANSWER-Discrepancy between the known elevation of a benchmark and its measured elevation at the end of a the survey route. First order survey - CORRECT ANSWER-Closure error is <= 3mm(K)^.5 to 5mm(K)^.5 <=.12ft(M)^.5 to .020ft(M)^.5 k=length of leveling route M=length in miles

Typology: Exams

2024/2025

Available from 06/29/2025

Academicmaterials
Academicmaterials 🇺🇸

1

(1)

4K documents

1 / 4

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
CVEN 303 - Final Exam
Closure Error - CORRECT ANSWER-Discrepancy between the known elevation of a
benchmark and its measured elevation at the end of a the survey route.
First order survey - CORRECT ANSWER-Closure error is
<= 3mm(K)^.5 to 5mm(K)^.5
<=.12ft(M)^.5 to .020ft(M)^.5
k=length of leveling route
M=length in miles
Second Order Survey - CORRECT ANSWER-Closure error is
<= 6mm(K)^.5 to 8mm(K)^.5
<=.024ft(M)^.5 to .034ft(M)^.5
k=length of leveling route
M=length in miles
Third Order Survey - CORRECT ANSWER-Closure error is
<= 12mm(K)^.5
<=.059ft(M)^.5
k=length of leveling route
M=length in miles
Purpose of Profile Leveling - CORRECT ANSWER-Determine the elevations of the
ground surface along the centerline or edges of a planned route feature and measure
location of route features.
Rate of Grade - CORRECT ANSWER-Vertical rise or fall/Horizontal Distance
-% - CORRECT ANSWER-How to express a falling grade
+% - CORRECT ANSWER-How to express a rising grade
NAVSTAR - CORRECT ANSWER-Navigation Satellite Timing and Ranging GPS
GPS Segments - CORRECT ANSWER-User segment (receivers and measurements)
Space Segment (satellites)
Control Segment (control stations)
Space Segment - CORRECT ANSWER-six orbits
four satellites in each orbit
takes twelve hours for each satellite to orbit
12,600 miles above the earth's surface
pf3
pf4

Partial preview of the text

Download CVEN 303 - Final Exam Questions with 100 % Correct Answers | Verified and more Exams Advanced Education in PDF only on Docsity!

CVEN 303 - Final Exam

Closure Error - CORRECT ANSWER-Discrepancy between the known elevation of a benchmark and its measured elevation at the end of a the survey route. First order survey - CORRECT ANSWER-Closure error is <= 3mm(K)^.5 to 5mm(K)^. <=.12ft(M)^.5 to .020ft(M)^. k=length of leveling route M=length in miles Second Order Survey - CORRECT ANSWER-Closure error is <= 6mm(K)^.5 to 8mm(K)^. <=.024ft(M)^.5 to .034ft(M)^. k=length of leveling route M=length in miles Third Order Survey - CORRECT ANSWER-Closure error is <= 12mm(K)^. <=.059ft(M)^. k=length of leveling route M=length in miles Purpose of Profile Leveling - CORRECT ANSWER-Determine the elevations of the ground surface along the centerline or edges of a planned route feature and measure location of route features. Rate of Grade - CORRECT ANSWER-Vertical rise or fall/Horizontal Distance

  • % - CORRECT ANSWER-How to express a falling grade +% - CORRECT ANSWER-How to express a rising grade NAVSTAR - CORRECT ANSWER-Navigation Satellite Timing and Ranging GPS GPS Segments - CORRECT ANSWER-User segment (receivers and measurements) Space Segment (satellites) Control Segment (control stations) Space Segment - CORRECT ANSWER-six orbits four satellites in each orbit takes twelve hours for each satellite to orbit 12,600 miles above the earth's surface

Control Segment - CORRECT ANSWER-Five Monitoring Stations Each passes a monitoring station twice a day. Monitoring Stations - CORRECT ANSWER-Control altitude, speed, and position of a satellite. Control Surveys - CORRECT ANSWER-Used to establish reference points, elevations, and lines for use in other surveys. Curvature Error (c) - CORRECT ANSWER-Divergence between a level line and a horizontal line over a specified distance Refraction Error (r) - CORRECT ANSWER-All sight lines are refracted downwards by the earth's atmosphere. Benchmark - CORRECT ANSWER-Permanently affixed object with known elevation (altitude) and or horizontal location (usually brass or aluminum disk that is attached to a very stable foundation) Direct Leveling - CORRECT ANSWER-Line of sight is horizontal, so difference in elevation is measured directly. Advantage of Direct Leveling - CORRECT ANSWER-Most Accurate method of leveling Disadvantage of Direct Leveling - CORRECT ANSWER-Time consuming to move Trigonometric Leveling - CORRECT ANSWER-Line of sight is not horizontal, so the difference in elevation is computed from vertical angle and slope distance. Advantage of Trigonometric Leveling - CORRECT ANSWER-Takes less time to do this method. Disadvantage of Trigonometric Leveling - CORRECT ANSWER-Low to moderate precision when using this method. Universal Transvers Mercator (UTM) - CORRECT ANSWER-A global system developed by US Military Services. Sea Level Distance - CORRECT ANSWER-Sea Level Distance * Elevation Factor Grid Distance - CORRECT ANSWER-Sea Level Distance * Scale Factor or Surface Distance * Combined Factor

Line - CORRECT ANSWER-A sequence of two or more coordinate pairs Polygon - CORRECT ANSWER-Composed of one or more lines whose starting and ending coordinate pairs are the same Attribute - CORRECT ANSWER-Particular piece of data associated with a map feature in a GIS is called an attribute (stored in data tables) Spatial Relationship - CORRECT ANSWER-A relationship based on location, where the features are located in relation to one another (Distance, containment, intersection, adjacency)