Docsity
Docsity

Prepare for your exams
Prepare for your exams

Study with the several resources on Docsity


Earn points to download
Earn points to download

Earn points by helping other students or get them with a premium plan


Guidelines and tips
Guidelines and tips

Contract Law Case Study: Albrecht Construction Ltd v Philip and Michael, Study notes of Law

Contract Law Exam Notes. Contract Law Exam NotesContract Law Exam NotesContract Law Exam NotesContract Law Exam NotesContract Law Exam NotesContract Law Exam NotesContract Law Exam Notes

Typology: Study notes

2021/2022

Uploaded on 05/09/2023

tom-butler-1
tom-butler-1 🇬🇧

2 documents

1 / 3

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Facts
Albrecht Construction Ltd averaged tenders from subcontractors to put forward a bid for
the dressing room installation part of their bid for a contract to construct a new sports
arena.
INVITATION TO TENDER
Only 2 subcontractor bids: Philip and Michael
Deadline for subcontractors to submit their bids was 5pm on 31st March
Philip:
Facts:
Philip posted a bid approximately half the cost of Michael’s, which arrived on time and was
accepted- Postal Rule not applicable.
Philip’s bid was too low to be feasible for him due to an arithmetical error when drawing it
up- Mistake
Philip has informed Albrecht Construction Ltd of the error and that he will not be able to do
the job for that price- Mistake: Frustration?
Issue 1
Arithmetic errors
Not Frustration as the error occurred before the contract was made, although only coming
to light after the contract was agreed.
Common Mistake- The tender amount was wrong due to an arithmetic error.
Relevant Laws
Mistake-
Smith v Hughes [1871]- Facts must be viewed objectively by the court when deciding if the
mistake was sufficient to void the contract.
Amalgamated Investment and Property Co Ltd v John Walker and Sons Ltd [1977] 1 WLR
164- The mistake must precede the contract.
Common Mistake- Must not be the fault of one of the parties to void contract. The
arithmetical error is referred to as “his mistake”, therefore Philip assumes blame for the
mistake.
Common mistake must be the fault of neither party, and ‘fundamental’1 to the contract.
Centrovincial Estates plc v Merchant Investors Assurance Co. Ltd [1983] 3 WLUK 55- Where
an offeror makes an unambiguous offer to a third party, under a mistake which the party
ought not to be aware of, they are bound by an acceptance of the offer, as long as there is
consideration. “It is a well-established principle of the English law of contract that an offer
falls to be interpreted not subjectively by reference to what has actually passed through the
mind of the offeror, but objectively”. There is no reason for Albrecht Construction Ltd to be
aware of the error in the tender, therefore the contract will not be voided for common
1 Bell v Lever Bros Ltd [1932] AC 161.
pf3

Partial preview of the text

Download Contract Law Case Study: Albrecht Construction Ltd v Philip and Michael and more Study notes Law in PDF only on Docsity!

Facts Albrecht Construction Ltd averaged tenders from subcontractors to put forward a bid for the dressing room installation part of their bid for a contract to construct a new sports arena. INVITATION TO TENDER Only 2 subcontractor bids: Philip and Michael Deadline for subcontractors to submit their bids was 5pm on 31st^ March Philip: Facts: Philip posted a bid approximately half the cost of Michael’s, which arrived on time and was accepted- Postal Rule not applicable. Philip’s bid was too low to be feasible for him due to an arithmetical error when drawing it up- Mistake Philip has informed Albrecht Construction Ltd of the error and that he will not be able to do the job for that price- Mistake: Frustration? Issue 1 Arithmetic errors Not Frustration as the error occurred before the contract was made, although only coming to light after the contract was agreed. Common Mistake- The tender amount was wrong due to an arithmetic error. Relevant Laws Mistake- Smith v Hughes [1871]- Facts must be viewed objectively by the court when deciding if the mistake was sufficient to void the contract. Amalgamated Investment and Property Co Ltd v John Walker and Sons Ltd [1977] 1 WLR 164- The mistake must precede the contract. Common Mistake- Must not be the fault of one of the parties to void contract. The arithmetical error is referred to as “his mistake”, therefore Philip assumes blame for the mistake. Common mistake must be the fault of neither party, and ‘fundamental’^1 to the contract. Centrovincial Estates plc v Merchant Investors Assurance Co. Ltd [1983] 3 WLUK 55- Where an offeror makes an unambiguous offer to a third party, under a mistake which the party ought not to be aware of, they are bound by an acceptance of the offer, as long as there is consideration. “It is a well-established principle of the English law of contract that an offer falls to be interpreted not subjectively by reference to what has actually passed through the mind of the offeror, but objectively”. There is no reason for Albrecht Construction Ltd to be aware of the error in the tender, therefore the contract will not be voided for common (^1) Bell v Lever Bros Ltd [1932] AC 161.

mistake as it was Philip’s fault and Albrecht had no reason to suspect that the tender amount was wrong. Traditional Structures Ltd v HW Construction Ltd [2010] EWHC 1530 (TCC)- contract rectified after costs mistakenly omitted and the contractor was aware of the omission, failed to notify the subcontractor and benefitted from the mistake. Even if the subcontract cost is rectified, Albrecht Constructions Ltd’s overall construction contract would not be frustrated as performance of the construction is still possible: they would only incur profit losses. Issue 2 Anticipatory Breach Philip claims that ‘there is no way he could do the job at that price’, as we have established that he is legally bound to. Relevant Law Yukong Line of Korea v Rendsburg Investments Corporation of Liberia [1996] 2 LR 604- anticipatory breach is a renunciation of the contract by one of the parties prior to the time when performance was due. Anticipatory breach gives the other party the right to treat the contract as discharged through breach immediately. If a party says they will not perform, the other party can take them at their word and act accordingly. White & Carter (Councils) Ltd v McGregor [1962] AC 413 HL- After an anticipatory breach has been established and the innocent party has chosen to affirm the contract, they are entitled to claim for the entire value of the contract. Vitol SA v Norelf Ltd (The Santa Clara) [1996] AC 800- Actions of the innocent party can constitute acceptance of repudiation of the contract. SK Shipping (S) Pte Ltd v Petroexport Ltd [2009] EWHC 2974 (Comm)- An express statement that a party will not perform the contract as agreed amounts to an anticipatory repudiatory breach. Maredelanto Compania Naviera SA v Bergbau-Handel GmbH (The Mihalis Angelos) [1971] 1 QB 164- In my view, where there is an anticipatory breach of contract, the breach is the repudiation once it has been accepted, and the other party is entitled to recover by way of damages the true value of the contractual rights which he has thereby lost, subject to his duty to mitigate. If the contractual rights which he has lost were capable by the terms of the contract of being rendered either less valuable or valueless in certain events, and if it can be shown that those events were, at the date of acceptance of the repudiation, pre destined to happen, then in my view the damages which he can recover are not more than the true value, if any, of the rights which he has lost, having regard to those pre destined events. Expectation Loss Damages- Photo Production Ltd v Securicor Transport Ltd [1980] AC 827- Any breach of contract entitles the innocent party to monetary compensation for the breach. Farley v Skinner [2001] UKHL 49- damages for breach of contract seek to put the innocent party in the position they would have been in had the contract been performed properly. Chaplin v Hicks [1911] 2 KB 786- Expectation losses are calculated based on the probability that a party would have benefited from the contract.