Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
Community
Ask the community for help and clear up your study doubts
Discover the best universities in your country according to Docsity users
Free resources
Download our free guides on studying techniques, anxiety management strategies, and thesis advice from Docsity tutors
A comprehensive set of questions and answers for the asphalt field level i exam 2024. It covers various aspects of asphalt paving, including preconstruction planning, safety procedures, material handling, compaction techniques, and quality control. A valuable resource for individuals preparing for the exam, offering insights into key concepts and practical applications.
Typology: Exams
1 / 5
This page cannot be seen from the preview
Don't miss anything!
"The _________ should be held before work on a project begins to ensure agreement on the proposed schedule, methods to be used to complete the project on schedule, change orders, and
should be taken immediately, even if the paving operation must be shut down until the unsafe practice is changed"
proper training, communication"
dampening/flushing with water, sweeping with mechanical broom"
Diesel fuel should never be used as a release agent" "(T or F) Some mixed are more prone to segregation than other la and special care must be taken
"Hauling equipment (end dump or live bottom trucks) used to deliver mix to the paver should
"(T or F)The screed heater is more important because it prevents the mix from sticking out I the
"(T or F) When changing trucks during paving, it is best if the paver can be stopped briefly to allow
"(T or F) When forming a longitudinal joint, it is best not to overlap the cold joint with the end gate
- CORRECT ANSWER False"
ground temperature & windspeed"
0.04 to 0.08"
"(T or F) In general, the vibratory roller should be operated at as high a frequency as possible. The use of the highest possible frequency of vibration increases the number of impacts per foot at a
related problems & mixture related problems" "(T or F) Mat problems that occur at the time of asphalt mix production are due only to laydown
Washboarding"
Material segregation" "________ normally occurs when heavy traffic passes over an unstable or poorly compacted mix
under the screed, excessive wear on the back of the screed" "(Tor F) The interaction of paver speed l, material feed rate, and tow point elevation determine
offset from the joint in the layer below" "There are several variables associated with rollers that can be adjusted from job-to-job. These
over a given area of the mat, roller pattern" "The _________ is the first device used to compact the mat and may be operated in the vibratory
finish" "MAT Tearing or pulling of the asphalt mix under the screed of the paver is most often observed:
lane width" "______ is defined as a short transverse cracks which occur in the surface of the AC mat at some
Fluctuating hard of material, screws being set too low, screed plate being worn out, running hopper empty between loads"