





Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
Community
Ask the community for help and clear up your study doubts
Discover the best universities in your country according to Docsity users
Free resources
Download our free guides on studying techniques, anxiety management strategies, and thesis advice from Docsity tutors
it is related to the moot court preposition
Typology: Summaries
1 / 9
This page cannot be seen from the preview
Don't miss anything!
Aadhan Green Energy Limited (AGEL) states that the actions of Solar Water Corporation Limited (SWCL) leading up to the termination of the contract were arbitrary, and the settlement agreement was concluded under Duress. AGEL claims are supported by many provisions of the Indian Contract Act,1872 , that addresses the breach of contract, coercion, and the consequences of delayed payment. SUPPORTING POINTS Sec-15 of ICA, 1872: COERCION & DURESS Section 15 of the Indian contract act define Coercion , “Coercion is the committing or threatening to commit, any act forbidden by Indian Penal Code, or the unlawful detaining, or threatening to detain, any property, to the prejudice of any person whatever, with the intention of causing any person to enter into an agreement. DELAYED PAYMENTS AGEL were forced to agree to the settlement due to SWCL’s economic duress. As economic duress is not specifically mentioned in the ICA,1872, but in section 15, coercion includes act that threaten a party’s financial stability or well-being. SWCL delayed payment due to AGEL for work completed in September 2023 & October
2023. These delays continued for several months, which leads to the financial strain on AGEL (Clause 4 of the proposition). AGEL repeatedly requested for the payments from SWCL but did not receive them until March 2024, which affected AGEL’s ability to continue working on the project. Threat of withholding payments, imposing LDs, and reducing the scope of work under the contract amount as economic pressure on AGEL, thus amounting to coercion under the section 15 of ICA, 1872. EVIDENCE- The proposition clearly states that the non-release of payment by SWCL was causing “ severe financial distress ” to AGEL , which impacted its progress. REDUCTION OF WORK SCOPE On April,01 2024 SWCL issued a notice to AGEL to reduce the scope of work to 50% and imposed Liquidated Damages (LDs) for delay in completing the project. Sudden reduction of
the contract’s scope deprived AGEL of opportunity to earn from remaining part of the project, forced AGEL to accept disadvantageous terms(Clause 6 of Moot Preposition). THREAT OF INVOCATION OF THE ADVANCE PAYMENT BOND SWCL’s letter dated April 01, 2024 also required AGEL to pay the remaining advance payment of INR 7,50,00,000/- (7.5 crore Indian Rupees ) by April 30, 2024, failing of which , SWCL would invoke the advance payment bond. This amounts to further financial pressure on AGEL to agree to the settlement (Clause 6 c). SECTION 19 OF 1CA, 1872- Voidability of agreements without free consent.— When consent to an agreement is caused by coercion, fraud or misrepresentation, the agreement is a contract voidable at the option of the party whose consent was so caused. As from above points and evidences , it can be state that AGEL consented to the settlement under coercion & duress , hence the settlement between both the parties is voidable. GENUINE CONSENT WAS ABSENT The key argument for AGEL is that the settlement was not entered voluntarily but under economic duress. In Section 10 of ICA,1872 - All agreements are contracts if they are made by the free consent of parties competent to contract, for a lawful consideration and with a lawful object, and are not hereby expressly declared to be void. AGEL can show that the free consent element was not present, as evidenced by: Financial Pressure – The financial distress caused by the delayed payments created a situation where AGEL had no choice but to accept the settlement to avoid bankruptcy. Unequal Bargaining Power – SWCL is a public sector enterprise with govt. backing, had significantly more bargaining power and used this leverage to impose unfavourable settlement terms on AGEL. OTHER FACTOR- AGEL can highlight that SWCL acted in mala fide intention by delaying payments, reducing the scope of work and threatening to invoke bonds to gain an unfair advantage in the settlement process.
suspended its work due to financial distress caused by non-payment, can use this ruling to defend its decision to suspend the project. SECTION 56 – Doctrine of Frustration According to the section 56 of ICA, 1872, describes conditions when performance of contract become impossible due to an unforeseen event, not caused by the fault of either party. When a contract becomes impossible to perform , then the contract declared void. AGEL milestone was directly dependent on SWCL making the payment. As SWCL delayed payment for September and October 2023, put AGEL into difficult situation , unable to continue the work. Despite the willingness to perform the contract, AGEL couldn’t complete contract. Acc. to sec 56 of ICA when performance becomes impossible due to circumstances beyond the control of promisor ( i.e. AGEL), the contract is frustrated. SWCL reduced the scope of work of AGEL which amount to made the completion of the project impossible. AGEL was acting in good faith and attempting to meet deadlines, but SWCL’s actions frustrated the contract by changing its original terms. Hence due to SWCL’s delayed payments and reduction of scope , AGEL can seek relief under Section 56 to claim compensation for the investment made in machinery worth INR 2 Crores. Supporting Case Law
radically altered the original contract, frustrating AGEL's ability to perform as intended.
SECTION 73 – Compensation for breach of contract When a contract has been broken, the party who suffers by such breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it. SWCL failed to make payment on time to AGEL for the months of September and October 2023, even AGEL completed 24% of the project. The delay in payment caused financial distress to the AGEL, which led to delay in project. As per section 73 of ICA, AGEL is entitled to claim compensation for the losses it suffered due to SWCL’s failure to make payment which was obligated in the contract. Hence, the non payment by SWCL was a breach of contract which had consequences on AGEL’s working. SWCL reduced AGEL's scope of work by 50% on April 1, 2024, which affected AGEL’s financial interests, this reduction was done without proper reason and affected AGEL’s profits. under Section 73 AGEL can entitled to compensation for the loss of profit and opportunity caused by the reduced scope of work. the contract was terminated by SWCL on April 30, 2024, was wrongful and caused financial harm. SWCL’s non-payment and the reduction in the scope of work led to this situation, AGEL can claim compensation for the losses resulting from the contract’s termination. Under Section 73, AGEL is entitled to recover damages for the expected profits it would have earned had the contract been completed as originally agreed. Relevant Case Law